Northeast Building Project Approved by AA City Council

by aadl-news

The site plan and rezoning request for the third branch building project for the Ann Arbor District Library, a replacement for the NEB located in Plymouth Mall, were both unanimously approved at the August 10 City Council meeting. Construction documents are being finalized and the project will be bid out over the next two months. Groundbreaking is expected to occur in late September or early October and we anticipate a Spring 2008 opening.

The new branch will be located at the southwest corner of Traverwood and Huron Parkway, 1/2 mile from the current NE library branch location. The site plan includes on street parking, covered parking under the building and parking in an exposed lot south of the building.

This library branch was designed by VanTine|Guthrie Studio and will be constructed by O'Neal Construction.