Aerial Photograph of Willow Run Expressway Extension Construction, July 1954

Aerial Photograph of Willow Run Expressway Extension Construction, July 1954 image
Published In
Ann Arbor News, July 8, 1954
Caption
Extension of the Willow Run Expressway west beyond U-23 (Carpenter Rd.) and around Ann Arbor presents new traffic problems. Note the new side approaches and exits. West of this, is Stone School Rd. (not shown), where the overpass has been completed, and farther west on State Rd., work has begun on an overpass to be completed in October. When completed, the Expressway will reach US-12, west of Ann Arbor. State traffic counts show that traffic during an average day on US-23 near the Expressway totals 12,000 cars. There are 6,300 automobiles traveling on the Expressway near its US-23 terminus, the same survey disclosed. Completion date for the US-23 overpass is Nov. 15, 1955.

Year
1954
Month
July
Rights Held By
Donated by the Ann Arbor News. © The Ann Arbor News.