Huron High School under construction, July 1967 Photographer: Eck Stanger

Published In
Ann Arbor News, July 4, 1967
Caption
Building Of New High School Progresses Ann Arbor's second senior high school, Huron High School, continues to take shape at its site on Fuller near Geddes on the northeast side. The building, according to Sooren Gozmanian, the school district's planner-expediter, is on schedule for occupancy in September, 1968. Construction contracts totaling $9.3 million were let for the project last year. The school is designed to accommodate about 1,800 students in grades 10 through 12.
Ann Arbor News, July 4, 1967
Caption
Building Of New High School Progresses Ann Arbor's second senior high school, Huron High School, continues to take shape at its site on Fuller near Geddes on the northeast side. The building, according to Sooren Gozmanian, the school district's planner-expediter, is on schedule for occupancy in September, 1968. Construction contracts totaling $9.3 million were let for the project last year. The school is designed to accommodate about 1,800 students in grades 10 through 12.
Copyright
Copyright Protected
- Read more about Huron High School under construction, July 1967
- Log in or register to post comments
School Records Dry Out

Parent Issue
Day
3
Month
January
Year
1969
Copyright
Copyright Protected
- Read more about School Records Dry Out
- Log in or register to post comments
New Elementary School Named For Dr. King

Parent Issue
Day
11
Month
April
Year
1968
Copyright
Copyright Protected
- Read more about New Elementary School Named For Dr. King
- Log in or register to post comments
Tree Removals Deplored

Parent Issue
Day
7
Month
May
Year
1970
Copyright
Copyright Protected
- Read more about Tree Removals Deplored
- Log in or register to post comments
Administrators Ready For Move Into Huron High

Parent Issue
Day
10
Month
July
Year
1969
Copyright
Copyright Protected
- Read more about Administrators Ready For Move Into Huron High
- Log in or register to post comments
Huron High Will Be Ready, Official Says

Parent Issue
Day
8
Month
May
Year
1969
Copyright
Copyright Protected
- Read more about Huron High Will Be Ready, Official Says
- Log in or register to post comments
Planner Says Huron, King To Open In Fall

Parent Issue
Day
13
Month
March
Year
1969
Copyright
Copyright Protected
- Read more about Planner Says Huron, King To Open In Fall
- Log in or register to post comments
Superintendent To Talk About School Budget

Parent Issue
Day
11
Month
March
Year
1969
Copyright
Copyright Protected
- Read more about Superintendent To Talk About School Budget
- Log in or register to post comments
Board Told Huron And King Schools Still Scheduled For Opening In Fall

Parent Issue
Day
9
Month
January
Year
1969
Copyright
Copyright Protected
Hurron High Opening Delayed Until Next Fall

Parent Issue
Day
5
Month
December
Year
1968
Copyright
Copyright Protected
- Read more about Hurron High Opening Delayed Until Next Fall
- Log in or register to post comments